Spark North-East Link – Infrastructure Advice
OVERVIEW:
NEN Consulting was engaged by Spark North-East Link (NEL) to assess and verify the electrical design and load forecasts for two major construction sites – Manningham and Bulleen. Our role included identifying shortfalls, recommending improvements, and consolidating the final design into a verified package, including load schedules and backup power strategies.
Project budget: ~$14B
Spark North-East Link (NEL)
2024
Melbourne, VIC
UTILITIES CHALLENGE:
The project was affected by frequent scope changes, fluctuating responsibilities, and inconsistent design inputs.
NEN was initially responsible for full-site power planning but later transitioned into a verification role when the design scope shifted to a third- party contractor.
Bi-weekly design changes, combined with limited resourcing from Spark NEL, created a fragmented review process and delayed decision-making.
Coordinating evolving work areas across two sites made maintaining continuity and quality assurance a significant challenge.
SEAMLESS SOLUTION:
To address the challenges, NEN introduced a structured review process requiring full design consolidation before verification.
This eliminated the inefficiencies of iterative partial reviews and enabled quicker turnaround with more robust outcomes.
The final verified package included a comprehensive electrical design review – comprising load schedules, single line diagrams, reticulation plans, equipment layouts, and cost analysis for backup power solutions.
This approach ensured reliability and project continuity despite ongoing changes.
MULTIDISCIPLINARY APPROACH:
Our team was able to provide comprehensive support throughout the entire project, ensuring our scope of work was completed on time, on budget, and to the highest standard. Including:
- Electrical design review and load forecasting.
- Gap analysis and identification of supply shortfalls
- Consolidation and verification of third-party electrical designs.
- Cost analysis for backup power and alternative supply options.
- Preparation of site-wide load schedules and SLDs.
- Equipment layout and reticulation plan assessment.
- Project management to coordinate shifting design scope and timelines.
- Stakeholder engagement with Spark NEL and third- party contractors.
- Risk mitigation strategies for evolving design inputs.