Rail Projects Victoria – MAR Bulk Supply
OVERVIEW:
NEN Consulting was engaged by Rail Projects Victoria to assess and recommend bulk power supply options for the Melbourne Airport Rail project. The team navigated complex regulatory processes to secure a reliable and cost-effective transmission connection at Keilor Terminal Station.
Project budget: ~$13B
Rail Projects Victoria
2022 – Ongoing
Melbourne, VIC
UTILITIES CHALLENGE:
The project required a long-term, high-capacity power connection to support rail operations.
One of the key challenges was working with AEMO and AusNet to progress one of the first major transmission load connection in Victoria in several years.
Without a well-defined process, NEN Consulting had to ensure the state avoided unnecessary regulatory burdens while securing a fit-for- purpose solution.
SEAMLESS SOLUTION:
NEN Consulting conducted a multi-criteria analysis to assess various connection options based on reliability, feasibility, and cost.
The structured decision-making process included evaluating supply arrangements and energy procurement strategies.
The final recommendation provided Rail Projects Victoria with a robust, justifiable solution that was approved for implementation.
MULTIDISCIPLINARY APPROACH:
By proactively managing regulatory interactions and streamlining procurement, NEN Consulting ensured the successful selection of a bulk power supply solution that met project needs and government approval requirements. To support the decision-making process, NEN Consulting delivered:
- Multi-Criteria Analysis and Supply Options Reports
- Reliability and Tariff Modelling Reports
- Regulatory Advice and Compliance Guidance
- Stakeholder Coordination with AEMO, AusNet, and government agencies
- Ongoing process management, including approvals and meeting oversight
- Embedded network regulation advice for on-sale of electricity to station vendors